Briefing/projectactive
Montezuma Storage is a 185 MW Battery project in Texas, currently active.
Montezuma Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-01-30.
- Queue ID
- ERCOT-27INR0555
- Location
- Colorado, Texas
- Technology
- Battery
- Developer
- Montezuma Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- L_GLIDDE8_1Y; Bus number - 7258 138KV
What stands out
1
Montezuma Storage is a 185 MW Battery project in Texas with status active.
2
Montezuma Storage LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-01-30.
Market and operating context
- Queue date
- 2025-09-22
- Proposed COD
- 2029-01-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.