Query
Millers Branch Solar II
Type
Entity Briefing
Entity
Millers Branch Solar II
Generated
2026-10-19T15:01:20.110Z

Briefing on Millers Branch Solar II

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
178 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2026-05-01
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Millers Branch Solar II is a 178 MW Solar project in Texas, currently active.

Miller's Branch Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-05-01.

Queue ID
ERCOT-24INR0044
Location
Haskell, Texas
Technology
Solar
Developer
Miller's Branch Solar, LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)

What stands out

1

Millers Branch Solar II is a 178 MW Solar project in Texas with status active.

2

Miller's Branch Solar, LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-05-01.

Market and operating context

Queue date
2021-11-04
Proposed COD
2026-05-01
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Millers Branch Solar II — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0044
LocationHaskell, Texas
TechnologySolar
DeveloperMiller's Branch Solar, LLC
Market / regionERCOT
Point of interconnectionTap 345kV 60703 Gauss - 60514 Clear Crossing (60712 QUASAR)
Queue date2021-11-04
Proposed COD2026-05-01