Briefing/projectactive
Marcelina Storage is a 203 MW Battery project in Texas, currently active.
Marcelina Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2026-12-18.
- Queue ID
- ERCOT-23INR0318
- Location
- Wilson, Texas
- Technology
- Battery
- Developer
- Marcelina Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV 5133 Elm Creek - 5901 San Miguel
What stands out
1
Marcelina Storage is a 203 MW Battery project in Texas with status active.
2
Marcelina Solar, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2026-12-18.
Market and operating context
- Queue date
- 2021-08-09
- Proposed COD
- 2026-12-18
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.