300 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2029-06-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Mandolin Solar SLF is a 300 MW Solar+Battery project in Texas, currently active.

Mandolin Solar Project, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-06-15.

Queue ID
ERCOT-26INR0527
Location
Starr, Texas
Technology
Solar+Battery
Developer
Mandolin Solar Project, LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 80355 Del Sol - 80227 Rapido

What stands out

1

Mandolin Solar SLF is a 300 MW Solar+Battery project in Texas with status active.

2

Mandolin Solar Project, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-06-15.

Market and operating context

Queue date
2024-07-22
Proposed COD
2029-06-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Mandolin Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0527
LocationStarr, Texas
TechnologySolar+Battery
DeveloperMandolin Solar Project, LLC
Market / regionERCOT
Point of interconnectionTap 345kV 80355 Del Sol - 80227 Rapido
Queue date2024-07-22
Proposed COD2029-06-15