Briefing/projectactive
Malachite BESS is a 191 MW Solar+Battery project in Texas, currently active.
Malachite Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2032-04-30.
- Queue ID
- ERCOT-27INR0112
- Location
- Wharton, Texas
- Technology
- Solar+Battery
- Developer
- Malachite Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345 kV 44200 Hillje – 9073 Holman
What stands out
1
Malachite BESS is a 191 MW Solar+Battery project in Texas with status active.
2
Malachite Storage LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2032-04-30.
Market and operating context
- Queue date
- 2024-05-20
- Proposed COD
- 2032-04-30
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.