Briefing on Madera - Westover South 115 kV

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
110 MW
Proposed capacity
active
Current status
Wind
Technology
PJM
Market / region
Briefing/projectactive

Madera - Westover South 115 kV is a 110 MW Wind project in Pennsylvania, currently active.

Timing is limited to the current queue record.

Queue ID
PJM-AH1-746 - moved to TC2
Location
Clearfield, Pennsylvania
Technology
Wind
Market / region
PJM

What stands out

1

Madera - Westover South 115 kV is a 110 MW Wind project in Pennsylvania with status active.

Market and operating context

Queue date
2025-04-10
Service type
Generation Interconnection

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Madera - Westover South 115 kV — verified asset snapshot

FieldValue
Queue IDPJM-AH1-746 - moved to TC2
LocationClearfield, Pennsylvania
TechnologyWind
Market / regionPJM
Queue date2025-04-10
Service typeGeneration Interconnection