Query
M-Bar BESS I
Type
Entity Briefing
Entity
M-Bar BESS I
State
MD
Generated
2026-10-05T15:18:31.878Z

Briefing on M-Bar BESS I

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
82 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-09-18
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

M-Bar BESS I is a 82 MW Solar+Battery project in Texas, currently active.

M-Bar Energy I, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-18.

Queue ID
ERCOT-27INR0422
Location
Ector, Texas
Technology
Solar+Battery
Developer
M-Bar Energy I, LLC
Market / region
ERCOT
Point of interconnection
1141 Holt Switch Substation 138 kV

What stands out

1

M-Bar BESS I is a 82 MW Solar+Battery project in Texas with status active.

2

M-Bar Energy I, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-09-18.

Market and operating context

Queue date
2024-12-19
Proposed COD
2028-09-18
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

M-Bar BESS I — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0422
LocationEctor, Texas
TechnologySolar+Battery
DeveloperM-Bar Energy I, LLC
Market / regionERCOT
Point of interconnection1141 Holt Switch Substation 138 kV
Queue date2024-12-19
Proposed COD2028-09-18