Briefing on Lyra Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
500 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2027-09-15
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Lyra Solar is a 500 MW Solar+Battery project in Texas, currently active.

Juno Solar 4 is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-09-15.

Queue ID
ERCOT-27INR0434
Location
Borden, Texas
Technology
Solar+Battery
Developer
Juno Solar 4
Market / region
ERCOT
Point of interconnection
345kV MULESHOE (#59922)

What stands out

1

Lyra Solar is a 500 MW Solar+Battery project in Texas with status active.

2

Juno Solar 4 is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2027-09-15.

Market and operating context

Queue date
2025-03-24
Proposed COD
2027-09-15
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Lyra Solar — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0434
LocationBorden, Texas
TechnologySolar+Battery
DeveloperJuno Solar 4
Market / regionERCOT
Point of interconnection345kV MULESHOE (#59922)
Queue date2025-03-24
Proposed COD2027-09-15