Query
LONE STAR INDUSTRIAL PARK GAS POWER PROJECT
Type
Entity Briefing
Entity
LONE STAR INDUSTRIAL PARK GAS POWER PROJECT
State
AR
Technology
gas
Generated
2026-10-19T23:03:19.124Z

Briefing on LONE STAR INDUSTRIAL PARK GAS POWER PROJECT

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
166 MW
Proposed capacity
active
Current status
Gas
Technology
ERCOT
Market / region
2028-05-11
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

LONE STAR INDUSTRIAL PARK GAS POWER PROJECT is a 166 MW Gas project in Texas, currently active.

LONE STAR INDUSTRIAL PARK, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-05-11.

Queue ID
ERCOT-27INR0324
Location
Morris, Texas
Technology
Gas
Developer
LONE STAR INDUSTRIAL PARK, LLC
Market / region
ERCOT
Point of interconnection
1795 Monticello SES 138kV

What stands out

1

LONE STAR INDUSTRIAL PARK GAS POWER PROJECT is a 166 MW Gas project in Texas with status active.

2

LONE STAR INDUSTRIAL PARK, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-05-11.

Market and operating context

Queue date
2024-09-04
Proposed COD
2028-05-11
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

LONE STAR INDUSTRIAL PARK GAS POWER PROJECT — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0324
LocationMorris, Texas
TechnologyGas
DeveloperLONE STAR INDUSTRIAL PARK, LLC
Market / regionERCOT
Point of interconnection1795 Monticello SES 138kV
Queue date2024-09-04
Proposed COD2028-05-11