Briefing/projectactive
Laureles BESS is a 10 MW Battery project in Texas, currently active.
Regis Laureles is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2025-11-12.
- Queue ID
- ERCOT-23INR0499
- Location
- Cameron, Texas
- Technology
- Battery
- Developer
- Regis Laureles
- Market / region
- ERCOT
- Point of interconnection
- Station Name (TDSP Station Code) LAURELES; Load/Load Transformer Name LD01; PTI BUS number 5756; Voltage in kV (Transmission Level) 138kV
What stands out
1
Laureles BESS is a 10 MW Battery project in Texas with status active.
2
Regis Laureles is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2025-11-12.
Market and operating context
- Queue date
- 2022-10-21
- Proposed COD
- 2025-11-12
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.