Briefing on Kankakee Solar

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
144 MW
Proposed capacity
active
Current status
Solar
Technology
PJM
Market / region
2021-05-31
Proposed COD
TC1
Queue phase
Briefing/projectactive

Kankakee Solar is a 144 MW Solar project in Illinois, currently active.

AEUG Kankakee Solar, LLC is the reported developer. The reported queue phase is TC1. Proposed COD is 2021-05-31.

Queue ID
PJM-AF2-095
Location
Kankakee, Illinois
Technology
Solar
Developer
AEUG Kankakee Solar, LLC
Market / region
PJM
Point of interconnection
Davis Creek 138 kV

What stands out

1

Kankakee Solar is a 144 MW Solar project in Illinois with status active.

2

AEUG Kankakee Solar, LLC is the reported developer.

3

The reported queue phase is TC1; proposed COD is 2021-05-31.

Market and operating context

Queue date
2020-02-13
Proposed COD
2021-05-31
IA status
System Impact Study
Study phase
TC1
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Kankakee Solar — verified asset snapshot

FieldValue
Queue IDPJM-AF2-095
LocationKankakee, Illinois
TechnologySolar
DeveloperAEUG Kankakee Solar, LLC
Market / regionPJM
Point of interconnectionDavis Creek 138 kV
Queue date2020-02-13
Proposed COD2021-05-31