Briefing on Juanita Creek BESS

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
304 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2031-10-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Juanita Creek BESS is a 304 MW Battery project in Texas, currently active.

Juanita Creek Energy Center, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2031-10-01.

Queue ID
ERCOT-29INR0151
Location
Matagorda, Texas
Technology
Battery
Developer
Juanita Creek Energy Center, LLC
Market / region
ERCOT
Point of interconnection
Tap 345 kV 5915 South Texas Project - 44200 Hillje

What stands out

1

Juanita Creek BESS is a 304 MW Battery project in Texas with status active.

2

Juanita Creek Energy Center, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2031-10-01.

Market and operating context

Queue date
2025-06-19
Proposed COD
2031-10-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Juanita Creek BESS — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0151
LocationMatagorda, Texas
TechnologyBattery
DeveloperJuanita Creek Energy Center, LLC
Market / regionERCOT
Point of interconnectionTap 345 kV 5915 South Texas Project - 44200 Hillje
Queue date2025-06-19
Proposed COD2031-10-01