Briefing on Invictus Energy Storage

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
141 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-05-31
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Invictus Energy Storage is a 141 MW Battery project in Texas, currently active.

GSA Land Holdings is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-05-31.

Queue ID
ERCOT-23INR0794
Location
Coleman, Texas
Technology
Battery
Developer
GSA Land Holdings
Market / region
ERCOT
Point of interconnection
6390 FIREROCK4A 138kV

What stands out

1

Invictus Energy Storage is a 141 MW Battery project in Texas with status active.

2

GSA Land Holdings is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-05-31.

Market and operating context

Queue date
2024-01-03
Proposed COD
2028-05-31
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Invictus Energy Storage — verified asset snapshot

FieldValue
Queue IDERCOT-23INR0794
LocationColeman, Texas
TechnologyBattery
DeveloperGSA Land Holdings
Market / regionERCOT
Point of interconnection6390 FIREROCK4A 138kV
Queue date2024-01-03
Proposed COD2028-05-31