Briefing/projectsuspended
High Chaparral Solar 138kV is a 148 MW Solar project in Texas, currently suspended.
High Chaparral Solar Project, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2023-12-31.
- Queue ID
- ERCOT-23INR0157
- Location
- Brazoria, Texas
- Technology
- Solar
- Developer
- High Chaparral Solar Project, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 138kV 42110 Angleton - 42875 Danbury c04
What stands out
1
High Chaparral Solar 138kV is a 148 MW Solar project in Texas with status suspended.
2
High Chaparral Solar Project, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2023-12-31.
Market and operating context
- Queue date
- 2021-01-25
- Proposed COD
- 2023-12-31
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.