Query
Hermes Storage
Type
Entity Briefing
Entity
Hermes Storage
Generated
2026-10-19T06:22:31.657Z

Briefing on Hermes Storage

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
100 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2026-08-18
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Hermes Storage is a 100 MW Solar+Battery project in Texas, currently active.

Bell 1 Storage LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2026-08-18.

Queue ID
ERCOT-24INR0365
Location
Bell, Texas
Technology
Solar+Battery
Developer
Bell 1 Storage LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2

What stands out

1

Hermes Storage is a 100 MW Solar+Battery project in Texas with status active.

2

Bell 1 Storage LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2026-08-18.

Market and operating context

Queue date
2022-07-18
Proposed COD
2026-08-18
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Hermes Storage — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0365
LocationBell, Texas
TechnologySolar+Battery
DeveloperBell 1 Storage LLC
Market / regionERCOT
Point of interconnectionTap 345kV 3687 Bell County East Switch - 39950 TNP One Plant Ckt 2
Queue date2022-07-18
Proposed COD2026-08-18