Briefing on Hecate Energy Orem Wind

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
1.5 GW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2030-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Hecate Energy Orem Wind is a 1.5 GW Wind project in Texas, currently active.

Hecate Energy LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2030-06-01.

Queue ID
ERCOT-27INR0061
Location
Brazoria, Texas
Technology
Wind
Developer
Hecate Energy LLC
Market / region
ERCOT
Point of interconnection
42530 Jones Creek 345kV

What stands out

1

Hecate Energy Orem Wind is a 1.5 GW Wind project in Texas with status active.

2

Hecate Energy LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2030-06-01.

Market and operating context

Queue date
2023-06-28
Proposed COD
2030-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Hecate Energy Orem Wind — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0061
LocationBrazoria, Texas
TechnologyWind
DeveloperHecate Energy LLC
Market / regionERCOT
Point of interconnection42530 Jones Creek 345kV
Queue date2023-06-28
Proposed COD2030-06-01