Briefing/projectactive
Hastings Park BESS is a 256 MW Battery project in Texas, currently active.
Brazos Roots BESS, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-09-15.
- Queue ID
- ERCOT-26INR0551
- Location
- Brazoria, Texas
- Technology
- Battery
- Developer
- Brazos Roots BESS, LLC
- Market / region
- ERCOT
- Point of interconnection
- 39010 138kV HASTINGS
What stands out
1
Hastings Park BESS is a 256 MW Battery project in Texas with status active.
2
Brazos Roots BESS, LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-09-15.
Market and operating context
- Queue date
- 2024-08-16
- Proposed COD
- 2027-09-15
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.