Query
HARQUAHALA SUNRISE 2
Type
Entity Briefing
Entity
HARQUAHALA SUNRISE 2
Generated
2026-10-11T05:15:01.289Z

Briefing on HARQUAHALA SUNRISE 2

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
330 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2026-09-01
Proposed COD
C14
Queue phase
Briefing/projectactive

HARQUAHALA SUNRISE 2 is a 330 MW Solar+Battery project in Arizona, currently active.

The reported queue phase is C14. Proposed COD is 2026-09-01.

Queue ID
CAISO-2029
Location
Maricopa, Arizona
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Delaney Substation 500 kV

What stands out

1

HARQUAHALA SUNRISE 2 is a 330 MW Solar+Battery project in Arizona with status active.

2

The reported queue phase is C14; proposed COD is 2026-09-01.

Market and operating context

Queue date
2021-04-15
Proposed COD
2026-09-01
IA status
System Impact Study
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

HARQUAHALA SUNRISE 2 — verified asset snapshot

FieldValue
Queue IDCAISO-2029
LocationMaricopa, Arizona
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionDelaney Substation 500 kV
Queue date2021-04-15
Proposed COD2026-09-01
IA statusSystem Impact Study