Hanson Solar is a 399 MW Solar project in Texas, currently active.
Hanson Solar, LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-04-17.
- Queue ID
- ERCOT-23INR0086
- Location
- Coleman, Texas
- Technology
- Solar
- Developer
- Hanson Solar, LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 1444 Brown - 11406 Central Bluff
What stands out
Hanson Solar is a 399 MW Solar project in Texas with status active.
Hanson Solar, LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2027-04-17.
Latest linked story: “Cypress Creek Closes Financing for Hanson Solar, a 505MWdc Project Supporting Meta's Operations” (Energías Renovables, el periodismo de las energías limpias., 2025-11-21).
Market and operating context
- Queue date
- 2020-10-23
- Proposed COD
- 2027-04-17
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.