Briefing on Hammond Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
225 MW
Proposed capacity
active
Current status
Solar
Technology
Southeast
Market / region
2025-11-30
Proposed COD
System Impact Study
Queue phase
Briefing/projectactive

Hammond Solar is a 225 MW Solar project in Georgia, currently active.

The reported queue phase is System Impact Study. Proposed COD is 2025-11-30.

Queue ID
GTC-GI-181
Location
Floyd, Georgia
Technology
Solar
Market / region
Southeast
Point of interconnection
Hammond - Anniston 230 kV TL

What stands out

1

Hammond Solar is a 225 MW Solar project in Georgia with status active.

2

The reported queue phase is System Impact Study; proposed COD is 2025-11-30.

3

Latest linked story: “Georgia Power receives unanimous approval on 500MW BESS projects across the state” (Energy-Storage.News, 2024-12-10).

Market and operating context

Queue date
2023-09-19
Proposed COD
2025-11-30
IA status
System Impact Study
Study phase
System Impact Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Hammond Solar — verified asset snapshot

FieldValue
Queue IDGTC-GI-181
LocationFloyd, Georgia
TechnologySolar
Market / regionSoutheast
Point of interconnectionHammond - Anniston 230 kV TL
Queue date2023-09-19
Proposed COD2025-11-30