Briefing on Guajillo Wind

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
202 MW
Proposed capacity
active
Current status
Wind
Technology
ERCOT
Market / region
2028-09-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Guajillo Wind is a 202 MW Wind project in Texas, currently active.

Guajillo Wind LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-01.

Queue ID
ERCOT-28INR0168
Location
Duval, Texas
Technology
Wind
Developer
Guajillo Wind LLC
Market / region
ERCOT
Point of interconnection
Tap 345 kV 80079 Cruce - 5901 San Miguel CKT 01

What stands out

1

Guajillo Wind is a 202 MW Wind project in Texas with status active.

2

Guajillo Wind LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-09-01.

Market and operating context

Queue date
2024-12-19
Proposed COD
2028-09-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Guajillo Wind — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0168
LocationDuval, Texas
TechnologyWind
DeveloperGuajillo Wind LLC
Market / regionERCOT
Point of interconnectionTap 345 kV 80079 Cruce - 5901 San Miguel CKT 01
Queue date2024-12-19
Proposed COD2028-09-01