Query
GREENWOOD ENERGY STORAGE
Type
Entity Briefing
Entity
GREENWOOD ENERGY STORAGE
Technology
battery
Generated
2026-10-06T22:23:29.060Z

Briefing on GREENWOOD ENERGY STORAGE

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
252 MW
Proposed capacity
active
Current status
Battery
Technology
CAISO
Market / region
2032-05-26
Proposed COD
C14
Queue phase
Briefing/projectactive

GREENWOOD ENERGY STORAGE is a 252 MW Battery project in California, currently active.

The reported queue phase is C14. Proposed COD is 2032-05-26.

Queue ID
CAISO-2121
Location
Los Angeles, California
Technology
Battery
Market / region
CAISO
Point of interconnection
Mesa Substation 500 kV

What stands out

1

GREENWOOD ENERGY STORAGE is a 252 MW Battery project in California with status active.

2

The reported queue phase is C14; proposed COD is 2032-05-26.

Market and operating context

Queue date
2021-04-15
Proposed COD
2032-05-26
IA status
IA Executed
Study phase
C14
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

GREENWOOD ENERGY STORAGE — verified asset snapshot

FieldValue
Queue IDCAISO-2121
LocationLos Angeles, California
TechnologyBattery
Market / regionCAISO
Point of interconnectionMesa Substation 500 kV
Queue date2021-04-15
Proposed COD2032-05-26
IA statusIA Executed