Green Holly Solar is a 414 MW Solar project in Texas, currently suspended.
Copenhagen Infrastructure Partners Fund IV is the reported developer. The reported queue phase is IA Pending. Proposed COD is 2026-05-30.
- Queue ID
- ERCOT-21INR0021
- Location
- Dawson, Texas
- Technology
- Solar
- Developer
- Copenhagen Infrastructure Partners Fund IV
- Market / region
- ERCOT
- Point of interconnection
- tap 345kV 59900 Longdraw - 79641 Farmland
What stands out
Green Holly Solar is a 414 MW Solar project in Texas with status suspended.
Copenhagen Infrastructure Partners Fund IV is the reported developer.
The reported queue phase is IA Pending; proposed COD is 2026-05-30.
Latest linked story: “Sheep Will Make Room For 500,000 Honeybees In New Agrivoltaic Project” (CleanTechnica, 2025-06-01).
Market and operating context
- Queue date
- 2018-07-10
- Proposed COD
- 2026-05-30
- IA status
- IA Pending
- Study phase
- IA Pending
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.