Briefing/projectactive
Great Hambino BESS is a 123 MW Battery project in Texas, currently active.
Atascosa BESS, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-10-01.
- Queue ID
- ERCOT-26INR0654
- Location
- Atascosa, Texas
- Technology
- Battery
- Developer
- Atascosa BESS, LLC
- Market / region
- ERCOT
- Point of interconnection
- #5700 Miracle Lake Substation 138kV
What stands out
1
Great Hambino BESS is a 123 MW Battery project in Texas with status active.
2
Atascosa BESS, LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2027-10-01.
Market and operating context
- Queue date
- 2025-09-11
- Proposed COD
- 2027-10-01
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.