Briefing on Grayback Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
222 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2029-09-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Grayback Solar is a 222 MW Solar project in Texas, currently active.

Grayback Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-09-01.

Queue ID
ERCOT-28INR0464
Location
Wilbarger, Texas
Technology
Solar
Developer
Grayback Solar, LLC
Market / region
ERCOT
Point of interconnection
To Riley7A Substation (#6101)

What stands out

1

Grayback Solar is a 222 MW Solar project in Texas with status active.

2

Grayback Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-09-01.

Market and operating context

Queue date
2025-11-05
Proposed COD
2029-09-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Grayback Solar — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0464
LocationWilbarger, Texas
TechnologySolar
DeveloperGrayback Solar, LLC
Market / regionERCOT
Point of interconnectionTo Riley7A Substation (#6101)
Queue date2025-11-05
Proposed COD2029-09-01