Query
Goldenrod Wind
Type
Entity Briefing
Entity
Goldenrod Wind
Generated
2026-10-13T07:25:19.147Z

Briefing on Goldenrod Wind

Entity Briefing
Generated Oct 13, 2026·Dataset freshness not reported
39 MW
Proposed capacity
active
Current status
Wind
Technology
NYISO
Market / region
2029-12-01
Proposed COD
C24
Queue phase
Briefing/projectactive

Goldenrod Wind is a 39 MW Wind project in New York, currently active.

Goldenrod Wind LLC is the reported developer. The reported queue phase is C24. Proposed COD is 2029-12-01.

Queue ID
NYISO-C24-225
Location
Chautauqua, New York
Technology
Wind
Developer
Goldenrod Wind LLC
Market / region
NYISO
Point of interconnection
Moon Road-Hartfield 115kV Line159

What stands out

1

Goldenrod Wind is a 39 MW Wind project in New York with status active.

2

Goldenrod Wind LLC is the reported developer.

3

The reported queue phase is C24; proposed COD is 2029-12-01.

Market and operating context

Queue date
2024-09-20
Proposed COD
2029-12-01
Study phase
C24

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Goldenrod Wind — verified asset snapshot

FieldValue
Queue IDNYISO-C24-225
LocationChautauqua, New York
TechnologyWind
DeveloperGoldenrod Wind LLC
Market / regionNYISO
Point of interconnectionMoon Road-Hartfield 115kV Line159
Queue date2024-09-20
Proposed COD2029-12-01