Briefing on Golden Hills North Wind Energy Center

Entity Briefing
Generated Oct 17, 2026·Dataset freshness not reported
46 MW
Capacity
Operating
Current status
2017
Operating since
1
Generators
35.3%
Capacity factor
143 GWh
Annual generation
Briefing/plantOperating

Golden Hills North Wind Energy Center is a 46 MW Onshore Wind Turbine asset in CAISO (California), currently Operating.

Golden Hills North Wind Energy Center is reported in California since 2017 under NextEra Energy. Available operating and financial measures include 35.3% capacity factor and 143 GWh annual generation; $2254/kW reported CapEx.

Location
Alameda, California
Technology
Onshore Wind Turbine
Owner / parent
NextEra Energy
Operator
Golden Hills Interconnection Wind, LLC
Grid
CAISO (California)
Plant ID
61222

What stands out

1

Golden Hills North Wind Energy Center is a 46 MW Onshore Wind Turbine asset in California with status Operating.

2

Latest annual operating measures report 35.3% capacity factor and 143 GWh annual generation.

3

Available financial measures include $2254/kW CapEx.

4

Latest linked story: “Earnings call transcript: NextEra Energy Q1 2026 results beat EPS forecast” (Investing.com, 2026-04-28).

Market and operating context

ISO / market
CAISO (California)
Balancing authority
California Independent System Operator
NERC region
WECC
State rank
#52 of 116
National rank
#974 of 1,442

Why it matters

For this asset in CAISO (California), operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.