Briefing on Goat Mountain Wind-Repower

Entity Briefing
Generated Oct 5, 2026·Dataset freshness not reported
303 MW
Proposed capacity
active
Current status
Wind+Battery
Technology
ERCOT
Market / region
2027-06-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Goat Mountain Wind-Repower is a 303 MW Wind+Battery project in Texas, currently active.

NRG Energy is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-06-01.

Queue ID
ERCOT-27INR0367
Location
Sterling, Texas
Technology
Wind+Battery
Developer
NRG Energy
Market / region
ERCOT
Point of interconnection
76030 Gasconades Creek 345kV

What stands out

1

Goat Mountain Wind-Repower is a 303 MW Wind+Battery project in Texas with status active.

2

NRG Energy is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-06-01.

4

Latest linked story: “Clearway Energy: Combining Renewable Growth With Reliable Income” (Yahoo Finance, 2025-08-26).

Market and operating context

Queue date
2025-01-13
Proposed COD
2027-06-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Goat Mountain Wind-Repower — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0367
LocationSterling, Texas
TechnologyWind+Battery
DeveloperNRG Energy
Market / regionERCOT
Point of interconnection76030 Gasconades Creek 345kV
Queue date2025-01-13
Proposed COD2027-06-01