101 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-03-16
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Glasgow Storage is a 101 MW Solar+Battery project in Texas, currently active.

Glasgow Solar LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-03-16.

Queue ID
ERCOT-24INR0207
Location
Navarro, Texas
Technology
Solar+Battery
Developer
Glasgow Solar LLC
Market / region
ERCOT
Point of interconnection
Tap 345kV #2466 Big Onion - #68091 Navarro

What stands out

1

Glasgow Storage is a 101 MW Solar+Battery project in Texas with status active.

2

Glasgow Solar LLC is the reported developer.

3

The reported queue phase is IA Executed; proposed COD is 2028-03-16.

Market and operating context

Queue date
2022-02-21
Proposed COD
2028-03-16
IA status
IA Executed
Study phase
IA Executed

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Glasgow Storage — verified asset snapshot

FieldValue
Queue IDERCOT-24INR0207
LocationNavarro, Texas
TechnologySolar+Battery
DeveloperGlasgow Solar LLC
Market / regionERCOT
Point of interconnectionTap 345kV #2466 Big Onion - #68091 Navarro
Queue date2022-02-21