Briefing/projectactive
Glasgow Solar is a 204 MW Solar+Battery project in Texas, currently active.
Glasgow Solar LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2028-03-16.
- Queue ID
- ERCOT-24INR0206
- Location
- Navarro, Texas
- Technology
- Solar+Battery
- Developer
- Glasgow Solar LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV #2466 Big Onion - #68091 Navarro
What stands out
1
Glasgow Solar is a 204 MW Solar+Battery project in Texas with status active.
2
Glasgow Solar LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2028-03-16.
Market and operating context
- Queue date
- 2022-02-07
- Proposed COD
- 2028-03-16
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.