Briefing/projectactive
GATEWAY ENERGY STORAGE 2 is a 256 MW Battery project in California, currently active.
The reported queue phase is C14. Proposed COD is 2035-02-05.
- Queue ID
- CAISO-2185
- Location
- San Diego, California
- Technology
- Battery
- Market / region
- CAISO
- Point of interconnection
- Otay Mesa Switchyard 230 kV
What stands out
1
GATEWAY ENERGY STORAGE 2 is a 256 MW Battery project in California with status active.
2
The reported queue phase is C14; proposed COD is 2035-02-05.
3
Latest linked story: “Governor Newsom welcomes approval of Diablo Canyon license renewals, delivering on California’s commitment to a clean and reliable grid” (California State Portal | CA.gov, 2026-04-03).
Market and operating context
- Queue date
- 2021-04-15
- Proposed COD
- 2035-02-05
- IA status
- System Impact Study
- Study phase
- C14
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.