Briefing on Galaxy Solar 2

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
302 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2029-10-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Galaxy Solar 2 is a 302 MW Solar project in Texas, currently active.

Galaxy Solar 2, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-10-30.

Queue ID
ERCOT-28INR0385
Location
Ellis, Texas
Technology
Solar
Developer
Galaxy Solar 2, LLC
Market / region
ERCOT
Point of interconnection
3/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navarro Switch (LST) (#68091) BKR 3B3134/3B3127

What stands out

1

Galaxy Solar 2 is a 302 MW Solar project in Texas with status active.

2

Galaxy Solar 2, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-10-30.

Market and operating context

Queue date
2025-06-19
Proposed COD
2029-10-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Galaxy Solar 2 — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0385
LocationEllis, Texas
TechnologySolar
DeveloperGalaxy Solar 2, LLC
Market / regionERCOT
Point of interconnection3/4-Breaker Ring Bus at 345kV Venus Switch (#1907) BKR 4920 - Navarro Switch (LST) (#68091) BKR 3B3134/3B3127
Queue date2025-06-19
Proposed COD2029-10-30