Four Mile Hydropower Project is a 2 MW Conventional Hydroelectric asset in MISO (Midcontinent), currently Operating.
Four Mile Hydropower Project is reported in Michigan since 1990 under Eagle Creek Renewable Energy, LLC. Available operating and financial measures include 51.1% capacity factor and 9 GWh annual generation; $2294/kW reported CapEx.
- Location
- Alpena, Michigan
- Technology
- Conventional Hydroelectric
- Owner / parent
- Eagle Creek Renewable Energy, LLC
- Operator
- Eagle Creek Renewable Energy, LLC
- Grid
- MISO (Midcontinent)
- Plant ID
- 54341
What stands out
Four Mile Hydropower Project is a 2 MW Conventional Hydroelectric asset in Michigan with status Operating.
Latest annual operating measures report 51.1% capacity factor and 9 GWh annual generation.
Available financial measures include $2294/kW CapEx.
Market and operating context
- ISO / market
- MISO (Midcontinent)
- Balancing authority
- Midcontinent Independent Transmission System Operator, Inc..
- NERC region
- RFC
- State rank
- #36 of 51
- National rank
- #1203 of 1,462
Why it matters
For this asset in MISO (Midcontinent), operating status, generation, ownership, and linked events are the primary facts for performance and asset-level diligence. The exact chart and source-linked records below let the reader test those facts before moving to a deeper report.