Query
Fluvanna Max Solar SLF
Type
Entity Briefing
Entity
Fluvanna Max Solar SLF
Generated
2026-10-19T17:34:25.012Z

Briefing on Fluvanna Max Solar SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
153 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2029-09-14
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Fluvanna Max Solar SLF is a 153 MW Solar+Battery project in Texas, currently active.

Fluvanna Max Solar LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-09-14.

Queue ID
ERCOT-29INR0077
Location
Scurry, Texas
Technology
Solar+Battery
Developer
Fluvanna Max Solar LLC
Market / region
ERCOT
Point of interconnection
11305 DERMOTT 345 kV

What stands out

1

Fluvanna Max Solar SLF is a 153 MW Solar+Battery project in Texas with status active.

2

Fluvanna Max Solar LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2029-09-14.

Market and operating context

Queue date
2024-12-19
Proposed COD
2029-09-14
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Fluvanna Max Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-29INR0077
LocationScurry, Texas
TechnologySolar+Battery
DeveloperFluvanna Max Solar LLC
Market / regionERCOT
Point of interconnection11305 DERMOTT 345 kV
Queue date2024-12-19
Proposed COD2029-09-14