Briefing on Flatrock Creek Storage I

Entity Briefing
Generated Oct 11, 2026·Dataset freshness not reported
50 MW
Proposed capacity
active
Current status
Battery
Technology
PJM
Market / region
2029-12-31
Proposed COD
IA Executed
Queue phase
Briefing/projectactive

Flatrock Creek Storage I is a 50 MW Battery project in Indiana, currently active.

The reported queue phase is IA Executed. Proposed COD is 2029-12-31.

Queue ID
PJM-AG1-366
Location
Allen, Indiana
Technology
Battery
Market / region
PJM
Point of interconnection
Allen 345 kV

What stands out

1

Flatrock Creek Storage I is a 50 MW Battery project in Indiana with status active.

2

The reported queue phase is IA Executed; proposed COD is 2029-12-31.

3

Latest linked story: “The Tennessee Valley Authority Is Considering Building A Major New Energy Facility Near Flat Rock” (Discover Dade, 2025-06-03).

Market and operating context

Queue date
2020-09-30
Proposed COD
2029-12-31
IA status
IA Executed
Study phase
IA Executed
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Flatrock Creek Storage I — verified asset snapshot

FieldValue
Queue IDPJM-AG1-366
LocationAllen, Indiana
TechnologyBattery
Market / regionPJM
Point of interconnectionAllen 345 kV
Queue date2020-09-30
Proposed COD2029-12-31
IA statusIA Executed