Briefing on Fallstone Solar SLF

Entity Briefing
Generated Oct 20, 2026·Dataset freshness not reported
61 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-09-21
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Fallstone Solar SLF is a 61 MW Solar+Battery project in Texas, currently active.

Fallstone Solar, LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-09-21.

Queue ID
ERCOT-28INR0147
Location
Falls, Texas
Technology
Solar+Battery
Developer
Fallstone Solar, LLC
Market / region
ERCOT
Point of interconnection
Tap 69kV 3588 Groesbeck - 3637 Otto Junction

What stands out

1

Fallstone Solar SLF is a 61 MW Solar+Battery project in Texas with status active.

2

Fallstone Solar, LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-09-21.

Market and operating context

Queue date
2024-12-19
Proposed COD
2028-09-21
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Fallstone Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0147
LocationFalls, Texas
TechnologySolar+Battery
DeveloperFallstone Solar, LLC
Market / regionERCOT
Point of interconnectionTap 69kV 3588 Groesbeck - 3637 Otto Junction
Queue date2024-12-19
Proposed COD2028-09-21