Empire Central BESS is a 10 MW Battery project in Texas, currently active.
SMT Dallas III is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2025-12-19.
- Queue ID
- ERCOT-24INR0659
- Location
- Dallas, Texas
- Technology
- Battery
- Developer
- SMT Dallas III
- Market / region
- ERCOT
- Point of interconnection
- Station name: EMPCT, Load name: LDLXFMR2, XFMR Number: 2, Bus Number:2799, Voltage: 138kV
What stands out
1
Empire Central BESS is a 10 MW Battery project in Texas with status active.
2
SMT Dallas III is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2025-12-19.
Market and operating context
- Queue date
- 2024-01-29
- Proposed COD
- 2025-12-19
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.