Briefing/projectactive
Eligius BESS is a 175 MW Battery project in Texas, currently active.
Eligius Storage LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-11-28.
- Queue ID
- ERCOT-28INR0247
- Location
- Hidalgo, Texas
- Technology
- Battery
- Developer
- Eligius Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- tap 138kV Liston (#8394) – JL Bates (#8392) line, AEP
What stands out
1
Eligius BESS is a 175 MW Battery project in Texas with status active.
2
Eligius Storage LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2028-11-28.
Market and operating context
- Queue date
- 2025-02-25
- Proposed COD
- 2028-11-28
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.