Query
Edgewood BESS 1
Type
Entity Briefing
Entity
Edgewood BESS 1
State
TN
Technology
battery
Generated
2026-10-06T19:15:12.527Z

Briefing on Edgewood BESS 1

Entity Briefing
Generated Oct 6, 2026·Dataset freshness not reported
102 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2028-03-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Edgewood BESS 1 is a 102 MW Battery project in Texas, currently active.

Tempus Power management LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-03-01.

Queue ID
ERCOT-27INR0317
Location
Van Zandt, Texas
Technology
Battery
Developer
Tempus Power management LLC
Market / region
ERCOT
Point of interconnection
Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174)

What stands out

1

Edgewood BESS 1 is a 102 MW Battery project in Texas with status active.

2

Tempus Power management LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-03-01.

Market and operating context

Queue date
2024-11-21
Proposed COD
2028-03-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Edgewood BESS 1 — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0317
LocationVan Zandt, Texas
TechnologyBattery
DeveloperTempus Power management LLC
Market / regionERCOT
Point of interconnectionTap Edgewood 138kV bus(3181) to CANTNSW_8 (3174)
Queue date2024-11-21
Proposed COD2028-03-01