Briefing/projectactive
Drake BESS is a 257 MW Battery project in Texas, currently active.
Mallard Energy Storage LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-01-29.
- Queue ID
- ERCOT-25INR0101
- Location
- Collin, Texas
- Technology
- Battery
- Developer
- Mallard Energy Storage LLC
- Market / region
- ERCOT
- Point of interconnection
- #833 Wylie Switch 138kV
What stands out
1
Drake BESS is a 257 MW Battery project in Texas with status active.
2
Mallard Energy Storage LLC is the reported developer.
3
The reported queue phase is IA Executed; proposed COD is 2027-01-29.
Market and operating context
- Queue date
- 2022-06-02
- Proposed COD
- 2027-01-29
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.