Briefing/projectactive
Dovetail Solar 3 is a 666 MW Solar+Battery project in Texas, currently active.
Hecate Energy Dovetail Solar Holdings LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2029-04-20.
- Queue ID
- ERCOT-24INR0097
- Location
- Jack, Texas
- Technology
- Solar+Battery
- Developer
- Hecate Energy Dovetail Solar Holdings LLC
- Market / region
- ERCOT
- Point of interconnection
- Tap 345kV 1421 Willow Creek – 11523 THOMPRIC
What stands out
1
Dovetail Solar 3 is a 666 MW Solar+Battery project in Texas with status active.
2
Hecate Energy Dovetail Solar Holdings LLC is the reported developer.
3
The reported queue phase is Facility Study; proposed COD is 2029-04-20.
Market and operating context
- Queue date
- 2021-12-13
- Proposed COD
- 2029-04-20
- IA status
- Facility Study
- Study phase
- Facility Study
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.