Query
Donelson Solar SLF
Type
Entity Briefing
Entity
Donelson Solar SLF
Generated
2026-10-19T23:27:39.111Z

Briefing on Donelson Solar SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
75 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-10-17
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Donelson Solar SLF is a 75 MW Solar+Battery project in Texas, currently active.

Donelson Solar is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-10-17.

Queue ID
ERCOT-27INR0292
Location
Red River, Texas
Technology
Solar+Battery
Developer
Donelson Solar
Market / region
ERCOT
Point of interconnection
Tap the 69 kV Bagwell (#1785) - Clarksville (#11784) line, ONCOR

What stands out

1

Donelson Solar SLF is a 75 MW Solar+Battery project in Texas with status active.

2

Donelson Solar is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-10-17.

Market and operating context

Queue date
2025-03-24
Proposed COD
2028-10-17
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Donelson Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-27INR0292
LocationRed River, Texas
TechnologySolar+Battery
DeveloperDonelson Solar
Market / regionERCOT
Point of interconnectionTap the 69 kV Bagwell (#1785) - Clarksville (#11784) line, ONCOR
Queue date2025-03-24
Proposed COD2028-10-17