Briefing on DMF Sagerton Solar SLF

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
126 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
ERCOT
Market / region
2028-12-15
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

DMF Sagerton Solar SLF is a 126 MW Solar+Battery project in Texas, currently active.

Double Mountain Fork LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-12-15.

Queue ID
ERCOT-26INR0146
Location
Haskell, Texas
Technology
Solar+Battery
Developer
Double Mountain Fork LLC
Market / region
ERCOT
Point of interconnection
Tap 138kV 6158 Aspermont – 6161 Paint Creek

What stands out

1

DMF Sagerton Solar SLF is a 126 MW Solar+Battery project in Texas with status active.

2

Double Mountain Fork LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-12-15.

Market and operating context

Queue date
2023-07-31
Proposed COD
2028-12-15
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

DMF Sagerton Solar SLF — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0146
LocationHaskell, Texas
TechnologySolar+Battery
DeveloperDouble Mountain Fork LLC
Market / regionERCOT
Point of interconnectionTap 138kV 6158 Aspermont – 6161 Paint Creek
Queue date2023-07-31
Proposed COD2028-12-15