Query
Dilley Solar
Type
Entity Briefing
Entity
Dilley Solar
Generated
2026-10-19T10:23:08.225Z

Briefing on Dilley Solar

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Solar
Technology
ERCOT
Market / region
2028-06-30
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Dilley Solar is a 201 MW Solar project in Texas, currently active.

AETS Development Holdings LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2028-06-30.

Queue ID
ERCOT-28INR0461
Location
Frio, Texas
Technology
Solar
Developer
AETS Development Holdings LLC
Market / region
ERCOT
Point of interconnection
Tap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLS

What stands out

1

Dilley Solar is a 201 MW Solar project in Texas with status active.

2

AETS Development Holdings LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2028-06-30.

Market and operating context

Queue date
2025-12-23
Proposed COD
2028-06-30
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Dilley Solar — verified asset snapshot

FieldValue
Queue IDERCOT-28INR0461
LocationFrio, Texas
TechnologySolar
DeveloperAETS Development Holdings LLC
Market / regionERCOT
Point of interconnectionTap 138 kV 8212 DILLEY SWITCH AEP - 8613 BIG WELLS
Queue date2025-12-23
Proposed COD2028-06-30