Query
Desert Palm BESS
Type
Entity Briefing
Entity
Desert Palm BESS
State
TN
Technology
battery
Generated
2026-10-19T20:11:35.431Z

Briefing on Desert Palm BESS

Entity Briefing
Generated Oct 19, 2026·Dataset freshness not reported
201 MW
Proposed capacity
active
Current status
Battery
Technology
ERCOT
Market / region
2027-07-01
Proposed COD
Facility Study
Queue phase
Briefing/projectactive

Desert Palm BESS is a 201 MW Battery project in Texas, currently active.

Desert Palm BESS LLC is the reported developer. The reported queue phase is Facility Study. Proposed COD is 2027-07-01.

Queue ID
ERCOT-26INR0555
Location
Dimmit, Texas
Technology
Battery
Developer
Desert Palm BESS LLC
Market / region
ERCOT
Point of interconnection
78280 Bevo Substation 138 kV

What stands out

1

Desert Palm BESS is a 201 MW Battery project in Texas with status active.

2

Desert Palm BESS LLC is the reported developer.

3

The reported queue phase is Facility Study; proposed COD is 2027-07-01.

Market and operating context

Queue date
2024-08-16
Proposed COD
2027-07-01
IA status
Facility Study
Study phase
Facility Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Desert Palm BESS — verified asset snapshot

FieldValue
Queue IDERCOT-26INR0555
LocationDimmit, Texas
TechnologyBattery
DeveloperDesert Palm BESS LLC
Market / regionERCOT
Point of interconnection78280 Bevo Substation 138 kV
Queue date2024-08-16
Proposed COD2027-07-01