Query
DAYLIGHT queue pipeline — 1 projects by technology and status
Type
Entity Briefing
Entity
DAYLIGHT
ISO/RTO
isone
Generated
2026-10-12T11:23:43.797Z

Briefing on DAYLIGHT

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
611 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
CAISO
Market / region
2028-01-19
Proposed COD
C09
Queue phase
Briefing/projectactive

DAYLIGHT is a 611 MW Solar+Battery project in California, currently active.

The reported queue phase is C09. Proposed COD is 2028-01-19.

Queue ID
CAISO-1223
Location
Kings, California
Technology
Solar+Battery
Market / region
CAISO
Point of interconnection
Mustang 230 kV

What stands out

1

DAYLIGHT is a 611 MW Solar+Battery project in California with status active.

2

The reported queue phase is C09; proposed COD is 2028-01-19.

3

Latest linked story: “Baldy Mesa solar + storage project now online and supporting Amazon operations” (Solar Power World, 2024-05-21).

Market and operating context

Queue date
2016-05-02
Proposed COD
2028-01-19
IA status
IA Executed
Study phase
C09
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

DAYLIGHT — verified asset snapshot

FieldValue
Queue IDCAISO-1223
LocationKings, California
TechnologySolar+Battery
Market / regionCAISO
Point of interconnectionMustang 230 kV
Queue date2016-05-02
Proposed COD2028-01-19
IA statusIA Executed