Briefing on CVOW 1, OSS 1 - T1L11

Entity Briefing
Generated Oct 12, 2026·Dataset freshness not reported
833 MW
Proposed capacity
active
Current status
Offshore Wind
Technology
PJM
Market / region
2032-12-31
Proposed COD
TC1
Queue phase
Briefing/projectactive

CVOW 1, OSS 1 - T1L11 is a 833 MW Offshore Wind project in Virginia, currently active.

Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) is the reported developer. The reported queue phase is TC1. Proposed COD is 2032-12-31.

Queue ID
PJM-AF1-123
Location
City Of Chesapeake, Virginia
Technology
Offshore Wind
Developer
Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Market / region
PJM
Point of interconnection
Harper 230 kV

What stands out

1

CVOW 1, OSS 1 - T1L11 is a 833 MW Offshore Wind project in Virginia with status active.

2

Virginia Electric and Power Company (d/b/a Dominion Energy Virginia) is the reported developer.

3

The reported queue phase is TC1; proposed COD is 2032-12-31.

Market and operating context

Queue date
2019-09-17
Proposed COD
2032-12-31
IA status
IA Pending
Study phase
TC1
Service type
NRIS

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

CVOW 1, OSS 1 - T1L11 — verified asset snapshot

FieldValue
Queue IDPJM-AF1-123
LocationCity Of Chesapeake, Virginia
TechnologyOffshore Wind
DeveloperVirginia Electric and Power Company (d/b/a Dominion Energy Virginia)
Market / regionPJM
Point of interconnectionHarper 230 kV
Queue date2019-09-17
Proposed COD2032-12-31