Crossroads Wind is a 277 MW Wind project in Texas, currently active.
HyFuels Green Lake Wind LLC is the reported developer. The reported queue phase is IA Executed. Proposed COD is 2027-06-30.
- Queue ID
- ERCOT-26INR0021
- Location
- Victoria, Texas
- Technology
- Wind
- Developer
- HyFuels Green Lake Wind LLC
- Market / region
- ERCOT
- Point of interconnection
- 80090 Dokmai 138 KV
What stands out
Crossroads Wind is a 277 MW Wind project in Texas with status active.
HyFuels Green Lake Wind LLC is the reported developer.
The reported queue phase is IA Executed; proposed COD is 2027-06-30.
Latest linked story: “Top 4 Wind Energy Stocks to Consider Buoyed by Solid Market Trends” (Yahoo Finance, 2025-03-07).
Market and operating context
- Queue date
- 2022-09-27
- Proposed COD
- 2027-06-30
- IA status
- IA Executed
- Study phase
- IA Executed
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.