Briefing on Crawford Solar

Entity Briefing
Generated Oct 10, 2026·Dataset freshness not reported
160 MW
Proposed capacity
active
Current status
Solar+Battery
Technology
Southeast
Market / region
2025-12-31
Proposed COD
System Impact Study
Queue phase
Briefing/projectactive

Crawford Solar is a 160 MW Solar+Battery project in Georgia, currently active.

The reported queue phase is System Impact Study. Proposed COD is 2025-12-31.

Queue ID
GTC-GI-164
Location
Crawford, Georgia
Technology
Solar+Battery
Market / region
Southeast
Point of interconnection
Dorsett(GTC)-Thomaston 230 kV TL

What stands out

1

Crawford Solar is a 160 MW Solar+Battery project in Georgia with status active.

2

The reported queue phase is System Impact Study; proposed COD is 2025-12-31.

Market and operating context

Queue date
2022-06-07
Proposed COD
2025-12-31
IA status
System Impact Study
Study phase
System Impact Study

Why it matters

Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.

Crawford Solar — verified asset snapshot

FieldValue
Queue IDGTC-GI-164
LocationCrawford, Georgia
TechnologySolar+Battery
Market / regionSoutheast
Point of interconnectionDorsett(GTC)-Thomaston 230 kV TL
Queue date2022-06-07
Proposed COD2025-12-31
IA statusSystem Impact Study