Briefing/projectactive
CPC WEST is a 750 MW Wind+Battery project in California, currently active.
The reported queue phase is IA Executed. Proposed COD is 2026-07-05.
- Queue ID
- CAISO-96
- Location
- Kern, California
- Technology
- Wind+Battery
- Market / region
- CAISO
- Point of interconnection
- Tehachapi Conceptual Substation #1
What stands out
1
CPC WEST is a 750 MW Wind+Battery project in California with status active.
2
The reported queue phase is IA Executed; proposed COD is 2026-07-05.
Market and operating context
- Queue date
- 2006-03-01
- Proposed COD
- 2026-07-05
- IA status
- IA Executed
- Study phase
- IA Executed
- Service type
- NRIS
Why it matters
Queue phase, proposed timing, developer identity, and linked events determine how much of the stated pipeline should be treated as actionable development capacity. The project page and deeper report preserve those fields for further diligence.